Substation Scout

Greyhound Solar

ERCOT queue ID 21INR0268

Queue ID21INR0268
Project nameGreyhound Solar
Status (as published)SS Completed, FIS Completed, IA
SubstationTap Wolf - Moss
Point of interconnectionTap 345kV 11010 Wolf - 1018 Moss
CountyEctor
StateTX
Voltage345 kV
Capacity335.5 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2026-06-30
Source datasetlarge

Additional filed fields

Interconnecting EntityRockhound Solar 2, LLC dba "Greyhound Solar"
Cdr ZoneWEST
Fuel CodeSOL
Technology CodePV
Ia Signed44576
Screening Study Complete43621
Fis Approved45596
Air PermitNot Required
Water AvailabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.