Trinity Hills Wind repower

ERCOT queue ID 20INR0019

Queue ID20INR0019
Project nameTrinity Hills Wind repower
Status (as published)SS Completed, FIS Completed, IA
SubstationGarvey Rd
Point of interconnection17002 Garvey Rd 345kV
CountyYoung
StateTX
Voltage345 kV
Capacity-27 MW
Resource (as published)WIN/WT
Resource categoryWind (normalised for filtering)
Target commercial operation2026-08-29
Source datasetlarge

Additional filed fields

Interconnecting EntityTrinity Hills Wind Farm LLC
Cdr ZoneWEST
Fuel CodeWIN
Technology CodeWT
Ia Signed43390
Screening Study Complete42986
Fis Approved43314
Air PermitNot Required
Water AvailabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.