Substation Scout

Elbow Creek repower

ERCOT queue ID 19INR0174

Queue ID19INR0174
Project nameElbow Creek repower
Status (as published)SS Completed, FIS Completed, IA
SubstationLongshore
Point of interconnection1058 Longshore 345kV
CountyHoward
StateTX
Voltage345 kV
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)WIN/WT
Resource categoryWind (normalised for filtering)
Target commercial operation2027-03-31
Source datasetlarge

Additional filed fields

Interconnecting EntityElbow Creek Wind Project, LLC
Cdr ZoneWEST
Fuel CodeWIN
Technology CodeWT
Ia Signed39416
Screening Study Complete43238
Fis Approved43360
Air PermitNot Required
Water AvailabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.