Substation Scout

Big Sampson Wind

ERCOT queue ID 16INR0104

Queue ID16INR0104
Project nameBig Sampson Wind
Status (as published)SS Completed, FIS Completed, IA
Substationtap Cedar Canyon - Noelke
Point of interconnectiontap 345kV 76015 Cedar Canyon - 7053 Noelke
CountyCrockett
StateTX
Voltage345 kV
Capacity265.4 MW
Resource (as published)WIN/WT
Resource categoryWind (normalised for filtering)
Target commercial operation2026-09-01
Source datasetlarge

Additional filed fields

Interconnecting EntityBig Sampson Wind Project, LLC
Cdr ZoneWEST
Fuel CodeWIN
Technology CodeWT
Ia Signed43777
Screening Study Complete42172
Fis Approved45595
Air PermitNot Required
Water AvailabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.