Substation Scout

Crockett, TX interconnection queue

9 active projects totalling 1,894.6 MW in the ERCOT queue, plus 1 with terminal status (shown greyed).

9active projects
1,894.6active MW
10total filed
Queue IDProjectkVMWResourceStatus
24INR0442 Midnight Sun Energy Storage 138 523.9 Battery SS Completed, FIS Started, IA
29INR0184 Gridline Solar n/r 400 Solar SS Completed, FIS Started, No IA
29INR0073 Oasis wind 138 300 Wind SS Started, FIS Started, No IA
16INR0104 Big Sampson Wind 345 265.4 Wind SS Completed, FIS Completed, IA
28INR0012 Shamrock II Wind n/r 256.6 Wind Inactive
25INR0489 Ranchero BESS 345 150 Battery SS Completed, FIS Started, No IA
26INR0365 BLACK BEAR SOLAR 138 102.9 Solar SS Completed, FIS Started, No IA
22INR0455 Blue Sky Sol 138 101.2 Solar SS Completed, FIS Started, IA
26INR0366 BLACK BEAR BESS 138 51.2 Battery SS Completed, FIS Started, No IA
25INR0216 Blue Sky Storage SLF 138 0 Battery SS Completed, FIS Started, No IA

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.