Dickens, TX interconnection queue

9 active projects totalling 2,316.9 MW in the ERCOT queue, plus 1 with terminal status (shown greyed).

9active projects
2,316.9active MW
10total filed
Queue IDProjectkVMWResourceStatus
27INR0195 CORUSCANT BESS 345 417.8 Battery SS Completed, FIS Started, No IA
25INR0151 Academy Wind n/r 304.6 Wind Inactive
29INR0192 Spurland Solar I 345 302.1 Solar SS Completed, FIS Started, No IA
28INR0288 Outrider BESS 345 302 Battery SS Completed, FIS Started, IA
28INR0169 Sanders Hollow Energy Center 345 292.6 Wind SS Completed, FIS Not Started, IA
25INR0173 Wolf Spring Storage 345 202.7 Battery SS Completed, FIS Completed, IA
29INR0195 Spurland Solar II 345 201.6 Solar SS Completed, FIS Started, No IA
23INR0089 Donegal Solar 345 201.6 Solar SS Completed, FIS Started, IA
25INR0165 Timberlakes Solar 345 200.7 Solar SS Completed, FIS Started, No IA
25INR0172 Wolf Spring Solar 345 195.8 Solar SS Completed, FIS Completed, IA

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.