Substation Scout

LaPine-Chiloquin No 1 line. substation interconnection queue

0 active projects totalling 0 MW in the BPA queue, plus 2 with terminal status (shown greyed).

0active projects
0active MW
2total filed
Queue IDProjectkVMWResourceStatus
G1019 Not reported 230 500 Solar WITHDRAWN
G1020 Not reported 230 500 Solar WITHDRAWN

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with BPA before relying on these figures.