Klamath, OR interconnection queue

3 active projects totalling 1,019 MW in the BPA queue, plus 17 with terminal status (shown greyed).

3active projects
1,019active MW
20total filed
Queue IDProjectkVMWResourceStatus
G0748 Not reported 500 1,403 Solar WITHDRAWN
G87 Peoples Energy Resources 500 1,200 Gas WITHDRAWN
G0501 Not reported 500 1,100 Gas WITHDRAWN
G0648 Not reported 500 1,100 Battery WITHDRAWN
G94 Peoples Energy Resources 500 600 Other WITHDRAWN
G0657 Not reported n/r 500 Solar STUDY
G1018 Not reported 230 500 Solar WITHDRAWN
G1019 Not reported 230 500 Solar WITHDRAWN
G1020 Not reported 230 500 Solar WITHDRAWN
G33 Tenaska Inc 500 450 Gas WITHDRAWN
G0607 Not reported 500 394 Battery WITHDRAWN
G0826 Not reported 500 280 Solar STUDY
G1017 Not reported 230 250 Solar WITHDRAWN
G0640 Not reported 230 239 Wind STUDY COMPLETED
G0658 Not reported 230 239 Wind WITHDRAWN
G0545 Not reported 230 200 Solar WITHDRAWN
G0747 Not reported 230 200 Solar WITHDRAWN
G0544 Not reported 230 80 Solar WITHDRAWN
G103 Telephone Flat 230 60 Other WITHDRAWN
G104 Fourmile Hill 230 60 Other WITHDRAWN

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with BPA before relying on these figures.