Substation Scout

BPA's Vantage Substation substation interconnection queue

1 active project totalling 500 MW in the BPA queue, plus 1 with terminal status (shown greyed).

1active projects
500active MW
2total filed
Queue IDProjectkVMWResourceStatus
G0656 Not reported 230 500 Battery E&P EXECUTED
G0632 Not reported 230 300 Solar WITHDRAWN

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with BPA before relying on these figures.