Klondike 3 Wind
BPA queue ID G124
| Queue ID | G124 |
|---|---|
| Project name | Klondike 3 Wind |
| Status (as published) | ENERGIZED |
| Substation | Klondike Schoolhouse |
| Point of interconnection | Klondike Schoolhouse 230kV |
| County | Wasco |
| State | OR |
| Voltage | 230 kV |
| Capacity | 300 MW |
| Resource (as published) | Wind Turbine/Wind Turbine |
| Resource category | Wind (normalised for filtering) |
| Target commercial operation | 2007-10-15 |
| Source dataset | bpa-generation |
Tracked changes
No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →
Additional filed fields
| Requestor | Klondike Wind Power III, LLC |
|---|---|
| Connection Type | GI |
| Interconnection Type | ERIS |
| Poi | Klondike Schoolhouse 230kV |
| Generator Type | Wind Turbine |
| Fuel Source | Wind Turbine |
| Nameplate Mw Total | 300 |
| Max Summer Mw | 300 |
| Max Winter Mw | 300 |
| Reason Not Completed | . |
| Comments | on-line October 2007, April 2008. |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.