Substation Scout

Not reported

BPA queue ID G1076

Queue IDG1076
Project nameNot reported
Status (as published)STUDY
SubstationMidway-Moxee # transmission line
Point of interconnectionMidway-Moxee #115 kV transmission line
CountyYakima
StateWA
Voltage115 kV
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)Battery/Energy Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2027-06-01
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

Connection TypeGI
Interconnection TypeNRIS & ERIS
PoiMidway-Moxee #115 kV transmission line
Generator TypeEnergy Storage
Fuel SourceBattery
Nameplate Mw Total46.5
Max Summer Mw0
Max Winter Mw0
Reason Not Completed.

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.