Substation Scout

Not reported

BPA queue ID G1063

Queue IDG1063
Project nameNot reported
Status (as published)STUDY
SubstationMorrow Flat
Point of interconnectionMorrow Flat 230kV
CountyUmatilla
StateOR
Voltage230 kV
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)Battery/Energy Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2026-12-01
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

Connection TypeGI
Interconnection TypeERIS
PoiMorrow Flat 230kV
Generator TypeEnergy Storage
Fuel SourceBattery
Nameplate Mw Total175
Max Summer Mw0
Max Winter Mw0
Reason Not Completed.
CommentsCombined output not to exceed 100 MW