Substation Scout

Not reported

BPA queue ID G1036

Queue IDG1036
Project nameNot reported
Status (as published)STUDY
SubstationBig Eddy-Troutdale No 1 line
Point of interconnectionBig Eddy-Troutdale No 1 230 kV line
CountyHood River
StateOR
Voltage230 kV
Capacity234 MW
Resource (as published)Wind Turbine/Wind Turbine
Resource categoryWind (normalised for filtering)
Target commercial operation2028-10-31
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

Connection TypeGI
Interconnection TypeNRIS & ERIS
PoiBig Eddy-Troutdale No 1 230 kV line
Generator TypeWind Turbine
Fuel SourceWind Turbine
Nameplate Mw Total234
Max Summer Mw234
Max Winter Mw234
ClusterTransition Cluster
Reason Not Completed.
CommentsLowerC2 Study Area

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.