Not reported

BPA queue ID G0745

Queue IDG0745
Project nameNot reported
Status (as published)STUDY
SubstationHatton tap to Connell tap
Point of interconnectionHatton tap to Connell tap
CountyAdams
StateWA
VoltageNot reported
Capacity100 MW
Resource (as published)Solar/Photovoltaic
Resource categorySolar (normalised for filtering)
Target commercial operation2026-12-31
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

Connection TypeGI
Interconnection TypeNRIS & ERIS
PoiHatton tap to Connell tap
Generator TypePhotovoltaic
Fuel SourceSolar
Nameplate Mw Total202.6
Max Summer Mw100
Max Winter Mw100
ClusterTransition Cluster
Reason Not Completed.
CommentsTriCities/Umatilla3 Study Area