Substation Scout

Not reported

BPA queue ID G0721

Queue IDG0721
Project nameNot reported
Status (as published)STUDY COMPLETED
SubstationFranklin - McNary line, at the new Bofer Canyon Substation
Point of interconnectionFranklin - McNary 230 kV line, at the new Bofer Canyon Substation
CountyBenton
StateWA
Voltage230 kV
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)Wind Turbine/Wind Turbine
Resource categoryWind (normalised for filtering)
Target commercial operation2024-11-15
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

Connection TypeGI
Interconnection TypeERIS
PoiFranklin - McNary 230 kV line, at the new Bofer Canyon Substation
Generator TypeWind Turbine
Fuel SourceWind Turbine
Nameplate Mw Total13.6
Max Summer Mw0
Max Winter Mw0
Reason Not Completed.