Not reported
BPA queue ID G0635
| Queue ID | G0635 |
|---|---|
| Project name | Not reported |
| Status (as published) | STUDY COMPLETED |
| Substation | Franklin - McNary transmission line. |
| Point of interconnection | Franklin - McNary 230 KV transmission line. |
| County | Benton |
| State | WA |
| Voltage | 230 kV |
| Capacity | 100 MW |
| Resource (as published) | Wind Turbine/Wind Turbine |
| Resource category | Wind (normalised for filtering) |
| Target commercial operation | 2021-10-01 |
| Source dataset | bpa-generation |
Tracked changes
No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →
Additional filed fields
| Connection Type | GI |
|---|---|
| Interconnection Type | NRIS & ERIS |
| Poi | Franklin - McNary 230 KV transmission line. |
| Generator Type | Wind Turbine |
| Fuel Source | Wind Turbine |
| Nameplate Mw Total | 100 |
| Max Summer Mw | 100 |
| Max Winter Mw | 100 |
| Reason Not Completed | . |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.