Substation Scout

Not reported

BPA queue ID G0608

Queue IDG0608
Project nameNot reported
Status (as published)STUDY
SubstationBPA's John Day Substation
Point of interconnectionBPA's John Day 500 kV Substation
CountyKlickitat
StateWA
Voltage500 kV
Capacity1,200 MW
Resource (as published)Battery/Energy Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2027-12-31
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

Connection TypeGI
Interconnection TypeNRIS & ERIS
PoiBPA's John Day 500 kV Substation
Generator TypeEnergy Storage
Fuel SourceBattery
Nameplate Mw Total1200
Max Summer Mw1200
Max Winter Mw1200
ClusterTransition Late Stage
Reason Not Completed.
CommentsWith grid-charging

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.