Substation Scout

Arlington Microgrid

BPA queue ID G0593

Queue IDG0593
Project nameArlington Microgrid
Status (as published)ENERGIZED
SubstationBPA's Murray Substation
Point of interconnectionBPA's Murray Substation
CountySnohomish
StateWA
VoltageNot reported
Capacity2 MW
Resource (as published)Solar/Photovoltaic
Resource categorySolar (normalised for filtering)
Target commercial operation2019-06-21
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

RequestorPublic Utility District No. 1 of Snohomish County
Connection TypeGI
Interconnection TypeERIS
PoiBPA's Murray Substation
Generator TypePhotovoltaic
Fuel SourceSolar
Nameplate Mw Total1
Max Summer Mw2
Max Winter Mw2
Reason Not Completed.
Comments1.5 MW Request. 500 kW AC solar array; 1 MW battery storage.

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.