Arlington Microgrid
BPA queue ID G0593
| Queue ID | G0593 |
|---|---|
| Project name | Arlington Microgrid |
| Status (as published) | ENERGIZED |
| Substation | BPA's Murray Substation |
| Point of interconnection | BPA's Murray Substation |
| County | Snohomish |
| State | WA |
| Voltage | Not reported |
| Capacity | 2 MW |
| Resource (as published) | Solar/Photovoltaic |
| Resource category | Solar (normalised for filtering) |
| Target commercial operation | 2019-06-21 |
| Source dataset | bpa-generation |
Tracked changes
No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →
Additional filed fields
| Requestor | Public Utility District No. 1 of Snohomish County |
|---|---|
| Connection Type | GI |
| Interconnection Type | ERIS |
| Poi | BPA's Murray Substation |
| Generator Type | Photovoltaic |
| Fuel Source | Solar |
| Nameplate Mw Total | 1 |
| Max Summer Mw | 2 |
| Max Winter Mw | 2 |
| Reason Not Completed | . |
| Comments | 1.5 MW Request. 500 kW AC solar array; 1 MW battery storage. |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.