Not reported

BPA queue ID G0586

Queue IDG0586
Project nameNot reported
Status (as published)STUDY COMPLETED
SubstationBPA's Spring Creek Substation.
Point of interconnectionBPA's Spring Creek 230 kV Substation.
CountyKlickitat
StateWA
Voltage230 kV
Capacity100 MW
Resource (as published)Solar/Photovoltaic
Resource categorySolar (normalised for filtering)
Target commercial operation2022-06-15
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

Connection TypeGI
Interconnection TypeNRIS & ERIS
PoiBPA's Spring Creek 230 kV Substation.
Generator TypePhotovoltaic
Fuel SourceSolar
Nameplate Mw Total100
Max Summer Mw100
Max Winter Mw100
Reason Not Completed.