Substation Scout

Not reported

BPA queue ID G0523

Queue IDG0523
Project nameNot reported
Status (as published)STUDY
SubstationBPA Maupin Substation
Point of interconnectionBPA Maupin 69 kV Substation
CountyWasco
StateOR
Voltage69 kV
Capacity13 MW
Resource (as published)Solar/Photovoltaic
Resource categorySolar (normalised for filtering)
Target commercial operation2018-12-31
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

Connection TypeGI
Interconnection TypeERIS
PoiBPA Maupin 69 kV Substation
Generator TypePhotovoltaic
Fuel SourceSolar
Nameplate Mw Total13
Max Summer Mw13
Max Winter Mw13
Reason Not Completed.

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.