NewSun Riley Project

BPA queue ID G0522

Queue IDG0522
Project nameNewSun Riley Project
Status (as published)ENERGIZED
SubstationBPA's Harney - Brasada line, tap. 10 - 20 miles west of Harney Substation.
Point of interconnectionBPA's Harney - Brasada line, 115 kV tap. 10 - 20 miles west of Harney Substation.
CountyHarney
StateOR
Voltage115 kV
Capacity20 MW
Resource (as published)Solar/Photovoltaic
Resource categorySolar (normalised for filtering)
Target commercial operation2018-12-31
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

RequestorRiley Interconnection LLC
Connection TypeGI
Interconnection TypeERIS
PoiBPA's Harney - Brasada line, 115 kV tap. 10 - 20 miles west of Harney Substation.
Generator TypePhotovoltaic
Fuel SourceSolar
Nameplate Mw Total20
Max Summer Mw20
Max Winter Mw20
Reason Not Completed.

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.