Queue IDG0518
Project nameHorn Rapids Solar Project
Status (as published)ENERGIZED
SubstationPole , City of Richland
Point of interconnectionPole 3401, City of Richland
CountyBenton
StateWA
VoltageNot reported
Capacity5 MW
Resource (as published)Solar/Photovoltaic
Resource categorySolar (normalised for filtering)
Target commercial operation2017-11-13
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

RequestorEnergy Northwest (CGS)
Connection TypeGI
Interconnection TypeERIS
PoiPole 3401, City of Richland
Generator TypePhotovoltaic
Fuel SourceSolar
Nameplate Mw Total4
Max Summer Mw5
Max Winter Mw5
Reason Not Completed.
Comments3.2 MW solar, 1 MW Battery