Horn Rapids Solar Project
BPA queue ID G0518
| Queue ID | G0518 |
|---|---|
| Project name | Horn Rapids Solar Project |
| Status (as published) | ENERGIZED |
| Substation | Pole , City of Richland |
| Point of interconnection | Pole 3401, City of Richland |
| County | Benton |
| State | WA |
| Voltage | Not reported |
| Capacity | 5 MW |
| Resource (as published) | Solar/Photovoltaic |
| Resource category | Solar (normalised for filtering) |
| Target commercial operation | 2017-11-13 |
| Source dataset | bpa-generation |
Tracked changes
No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →
Additional filed fields
| Requestor | Energy Northwest (CGS) |
|---|---|
| Connection Type | GI |
| Interconnection Type | ERIS |
| Poi | Pole 3401, City of Richland |
| Generator Type | Photovoltaic |
| Fuel Source | Solar |
| Nameplate Mw Total | 4 |
| Max Summer Mw | 5 |
| Max Winter Mw | 5 |
| Reason Not Completed | . |
| Comments | 3.2 MW solar, 1 MW Battery |