The Dalles Northshore Fishway Project

BPA queue ID G0476

Queue IDG0476
Project nameThe Dalles Northshore Fishway Project
Status (as published)ENERGIZED
SubstationExisting Interconnection Point at Spearfish Substation
Point of interconnectionExisting Interconnection Point at Spearfish Substation
CountyWasco
StateOR
VoltageNot reported
Capacity7 MW
Resource (as published)Water/Hydro
Resource categoryHydro (normalised for filtering)
Target commercial operation2012-11-12
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

RequestorNorthern Wasco County People's Utility District
Connection TypeGI
Interconnection TypeERIS
PoiExisting Interconnection Point at Spearfish Substation
Generator TypeHydro
Fuel SourceWater
Nameplate Mw Total7
Max Summer Mw7
Max Winter Mw7
Reason Not Completed.
CommentsOn-line January 2013