Substation Scout

Not reported

BPA queue ID G0363

Queue IDG0363
Project nameNot reported
Status (as published)STUDY COMPLETED
SubstationBPA's Boardman Substation
Point of interconnectionBPA's Boardman 230 kV Substation
CountyGilliam
StateOR
Voltage230 kV
Capacity204 MW
Resource (as published)Wind Turbine/Wind Turbine
Resource categoryWind (normalised for filtering)
Target commercial operation2012-11-01
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

Connection TypeGI
Interconnection TypeNRIS
PoiBPA's Boardman 230 kV Substation
Generator TypeWind Turbine
Fuel SourceWind Turbine
Nameplate Mw Total204
Max Summer Mw204
Max Winter Mw204
Reason Not Completed.
CommentsStudy Issued 11/1/2012