Project nameFlathead LFGTE Project
Status (as published)ENERGIZED
SubstationFlathead’s LaSalle Substation
Point of interconnectionFlathead’s LaSalle Substation
CountyFlathead
StateMT
VoltageNot reported
Capacity2 MW
Resource (as published)Biofuel/Steam Turbine
Resource categoryOther (normalised for filtering)
Target commercial operation2009-05-01
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

RequestorFlathead Electric Cooperative, Inc.
Connection TypeGI
Interconnection TypeERIS
PoiFlathead’s LaSalle Substation
Generator TypeSteam Turbine
Fuel SourceBiofuel
Nameplate Mw Total2
Max Summer Mw2
Max Winter Mw2
Reason Not Completed.
Commentson-line June 2009