Flathead, MT interconnection queue

5 active projects totalling 9.9 MW in the BPA queue.

5active projects
9.9active MW
5total filed
Queue IDProjectkVMWResourceStatus
G0468 Stoltze Land and Lumber Project 12.5 3 Other ENERGIZED
G0710 Landfill Gas to Energy Facility n/r 2.9 Other ENERGIZED
G0358 Flathead LFGTE Project n/r 2 Other ENERGIZED
G0469 Whitefish In-Line Hydroelectric Project n/r 1 Hydro ENERGIZED
G1085 Not reported n/r 1 Battery BPA COMPLETED

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with BPA before relying on these figures.