Substation Scout

King Estate Solar Generator Project

BPA queue ID G0332

Queue IDG0332
Project nameKing Estate Solar Generator Project
Status (as published)ENERGIZED
SubstationIntegrating in Lane Electric Coop's system (Fox Hollow Substation)
Point of interconnectionIntegrating in Lane Electric Coop's system (Fox Hollow Substation)
CountyLane
StateOR
VoltageNot reported
Capacity1 MW
Resource (as published)Solar/Photovoltaic
Resource categorySolar (normalised for filtering)
Target commercial operation2008-12-01
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

RequestorLane Electric Cooperative, Inc.
Connection TypeGI
Interconnection TypeNRIS
PoiIntegrating in Lane Electric Coop's system (Fox Hollow Substation)
Generator TypePhotovoltaic
Fuel SourceSolar
Nameplate Mw Total1
Max Summer Mw1
Max Winter Mw1
Reason Not Completed.
Commentson-line November 2009

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.