Hopkins Ridge Addition
BPA queue ID G0274
| Queue ID | G0274 |
|---|---|
| Project name | Hopkins Ridge Addition |
| Status (as published) | ENERGIZED |
| Substation | Tucannon River Switching Station |
| Point of interconnection | Tucannon River Switching Station |
| County | Columbia |
| State | WA |
| Voltage | Not reported |
| Capacity | 7 MW |
| Resource (as published) | Wind Turbine/Wind Turbine |
| Resource category | Wind (normalised for filtering) |
| Target commercial operation | 2008-08-01 |
| Source dataset | bpa-generation |
Tracked changes
No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →
Additional filed fields
| Requestor | Puget Sound Energy, Inc. |
|---|---|
| Connection Type | GI |
| Interconnection Type | NRIS |
| Poi | Tucannon River Switching Station |
| Generator Type | Wind Turbine |
| Fuel Source | Wind Turbine |
| Nameplate Mw Total | 7 |
| Max Summer Mw | 7 |
| Max Winter Mw | 7 |
| Reason Not Completed | . |
| Comments | on-line August 2008 |