Willow Creek and Horn Butte

BPA queue ID G0255

Queue IDG0255
Project nameWillow Creek and Horn Butte
Status (as published)ENERGIZED
SubstationBoardman-Alkali Line
Point of interconnectionBoardman-Alkali 115 kV Line
CountyGilliam
StateOR
Voltage115 kV
Capacity72 MW
Resource (as published)Wind Turbine/Wind Turbine
Resource categoryWind (normalised for filtering)
Target commercial operation2008-05-01
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

RequestorInvenergy Wind Development LLC
Connection TypeGI
Interconnection TypeERIS
PoiBoardman-Alkali 115 kV Line
Generator TypeWind Turbine
Fuel SourceWind Turbine
Nameplate Mw Total72
Max Summer Mw72
Max Winter Mw72
Reason Not Completed.
CommentsLGIA executed for Phase 1, 72 MW; on-line November 2008.