Substation Scout

Montague 2

BPA queue ID G0239

Queue IDG0239
Project nameMontague 2
Status (as published)ENERGIZED
SubstationBPA Slatt Substation
Point of interconnectionBPA Slatt Substation
CountyGilliam
StateOR
VoltageNot reported
Capacity202 MW
Resource (as published)Solar/Photovoltaic
Resource categorySolar (normalised for filtering)
Target commercial operation2010-07-01
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

RequestorAvangrid Power, LLC
Connection TypeGI
Interconnection TypeERIS
PoiBPA Slatt Substation
Generator TypePhotovoltaic
Fuel SourceSolar
Nameplate Mw Total202
Max Summer Mw202
Max Winter Mw202
Reason Not Completed.
CommentsFAS Study Issued 7/20/2008

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.