Waldwick

Named in 1 PJM planning document for 1 project, on July 7, 2026.

Not stateddescribed as
PSEGzone
—kV as printed
1mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
PSEG Transmission Zone: Baseline
b3794.1
Not printed $45.4M 6/1/2028 Not printed 2026-07-07
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Cost estimate
prior value printed on the same page
$29.6 M → $45.4M 2026-07-07 2026-07-07

Every mention

DateDocumentProjectWhat the document says about it
2026-07-07 TEAC
Item 15 - Reliability Analysis Update p. 6
PSEG Transmission Zone: Baseline No role wording

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.