South Second St.

Named in 2 PJM planning documents for 1 project, on October 8, 2024.

Existingdescribed as
PSEGzone
69/13kVkV as printed
2mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Plainfield Area
PSEG-2023-0012 · s3184.1
Engineering $6.5M 12/2029 Not printed 2024-10-08
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Mid-Atlantic
PSEG local plan submission for 2024 RTEP p. 13
Plainfield Area “Construct a third transformer at existing South Second St. Station”
69/13kV
2024-10-08 TEAC
Informational Only - PSEG Local Plan submission of supplemental project 2024 p. 13
Plainfield Area “Construct a third transformer at existing South Second St. Station”
69/13kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.