Maple Shade
Named in 2 PJM planning documents for 1 project, on November 12, 2026.
Work described at itdescribed as
PSEGzone
69kVkV as printed
2mentions
Projects naming this substation
Figures are from the most recent document naming each project, as printed. Each links to its page.
| Project | Status as printed | Cost estimate | In-service date | Customer load | As of |
|---|---|---|---|---|---|
| Cherry Hill Area PSEG-2026-0003 |
Conceptual | $162.1 M | 06/01/2032 | Not printed | 2026-11-12 SRRTEP Mid-Atlantic |
Other substations in this project
“Cherry Hill Area” also names 6 other substations, with what the most recent document says about each.
- Camden PSEG Work described at it — “Cut and loop 69kV line from Camden to Maple Shade.” (p. 4)
- Cherry Hill Station PSEG Work described at it — “Cherry Hill Station has been in service since 1955 and needs to be addressed due to deteriorating equipment material condition.” (p. 3)
- Hilltop PSEG Work described at it — “Increase 69kV line ratings from Hilltop to Runnemede Station.” (p. 4)
- Lawnside PSEG Not stated
- Runnemede Station PSEG, NJ Work described at it — “Increase 69kV line ratings from Hilltop to Runnemede Station.” (p. 4)
- Sharp Rd PSEG Expansion — “Expand Sharp Rd 69kV station to a ring bus.” (p. 4)
Changes between documents
Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.
| What changed | Printed values | Earlier | Later |
|---|---|---|---|
| Substations named | CAMDEN; CHERRY HILL; HILLTOP; LAWNSIDE; MAPLE SHADE; RUNNEMEDE; SHARP RD → CAMDEN; CHERRY HILL; HILLTOP; MAPLE SHADE; RUNNEMEDE | 2026-11-12 | 2026-11-12 |
| Substations named | CHERRY HILL → CAMDEN; CHERRY HILL; HILLTOP; LAWNSIDE; MAPLE SHADE; RUNNEMEDE; SHARP RD | 2026-07-17 | 2026-11-12 |
Every mention
| Date | Document | Project | What the document says about it |
|---|---|---|---|
| 2026-11-12 | SRRTEP Mid-Atlantic Item 06 - PSEG Supplemental Projects Presentation p. 4 |
Cherry Hill Area | “Cut and loop 69kV line from Camden to Maple Shade.” 69kV |
| 2026-11-12 | SRRTEP Mid-Atlantic Item 05 - PSEG Supplemental Projects Presentation p. 4 |
Cherry Hill Area | No role wording 69kV |
* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.
Before relying on any of this
- Names are machine-extracted from PDFs by a language model. Every exported name was checked to be printed in the PDF text; names read only from maps or diagrams are excluded.
- An entry is a name within a transmission zone, not a verified physical facility. The same name in two zones is two entries; spelling variants are merged only when they differ by punctuation, case or a generic suffix such as "Substation", or when a PJM document prints a rename for the same project (src/ingest/rtepAliases.json; the entry lists its old names).
- role is "new" only where a cited document phrase calls the substation new, describes constructing it, or calls it proposed (graded by src/lib/roleBasis.js), "existing" where a phrase describes work at it, otherwise "unknown".
- expansion is set on a substation that is not "new" where a cited phrase describes a new voltage level, a new or expanded yard, bus or bay, or a named load connected to it (graded by src/lib/expansionBasis.js). It reproduces what the document describes and adds nothing to it.
- Costs, dates, statuses and loads are the documents' own printed values for the most recent document that names the substation. Each one shipped here is printed on its cited page ("verification": "exact" or "on-page"); values that failed that check are withheld and counted in figures_withheld_unverified. None has been reviewed by a person.
- Zone is the transmission owner whose deck presented the project. PJM-SYSTEM marks names from PJM's own reliability decks, which span zones.
- A printed customer load is the amount a document states for a request. It says nothing about the substation's capability.