Named in 4 PJM planning documents for 2 projects, from October 8, 2025 to October 6, 2026.

Not stateddescribed as
PPLzone
69kVkV as printed
4mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Old Forge, PA
PPL-2024-0008 · s3558
Conceptual $5.5 M 12/01/2027 Not printed 2025-10-08
TEAC
PPL-2026-0020 Conceptual $1 M 02/01/2027 Not printed 2026-10-06
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named SULLIVAN TRAIL → AVOCA; STANTON; SULLIVAN TRAIL 2026-04-14 2026-10-06

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - PPL Local Plan Submission of the Supplemental Projects for 2026 p. 85
PPL-2026-0020 No role wording
2026-09-17* SRRTEP Mid-Atlantic
PPL local plan submission for 2026 RTEP p. 85
PPL-2026-0020 No role wording
69kV
2026-09-08* SRRTEP Mid-Atlantic
PPL local plan submission for 2025 RTEP p. 23
Old Forge, PA No role wording
69kV
2025-10-08 TEAC
Informational Only - PPL Local Plan Submission of the Supplemental Projects for 2025 p. 22
Old Forge, PA No role wording
69kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.