Wishing Star

Named in 2 PJM planning documents for 2 projects, from December 3, 2024 to January 7, 2025.

Not stateddescribed as
PJM system-widezone
500kVkV as printed
2mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Recommended Solution: 2024-W1-781
b4000.340
Not printed $34.01 M 6/1/2029 Not printed 2025-01-07
TEAC
2024W1 – Regional Cluster Preferred Solution: 2024-W1-781
2024-W1-781
Not printed $34.03 M 6/1/2029 Not printed 2024-12-03
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Cost estimate
prior value printed on the same page
$34.03 M → $34.01 M 2025-01-07 2025-01-07

Every mention

DateDocumentProjectWhat the document says about it
2025-01-07 TEAC
Item 12 - Reliability Analysis Update p. 71
Recommended Solution: 2024-W1-781 No role wording
500kV
2024-12-03 TEAC
Item 11 - Reliability Analysis Update p. 83
2024W1 – Regional Cluster Preferred Solution: 2024-W1-781 No role wording
500kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this