Buzzard Point

Named in 1 PJM planning document for 2 projects, on Not reported.

Existingdescribed as
PEPCOzone
138kVkV as printed
2mentions

Also printed as: Buzzard Point substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Buzzard Point 7TS Breaker Replacement
PEP-2023-006 · s3203.1
Engineering $675k 12/1/2024 Not printed 2026-09-08*
SRRTEP Mid-Atlantic
Buzzard Point 13B & 14B Breaker Replacements
PEP-2024-001 · s3312.1
Engineering $300k 12/31/2024 Not printed 2026-09-08*
SRRTEP Mid-Atlantic

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Mid-Atlantic
PEPCO local plan submission for 2024 RTEP p. 7
Buzzard Point 7TS Breaker Replacement “138kV circuit breaker 7TS at Buzzard Point substation was installed in 1972”
138kV
2026-09-08* SRRTEP Mid-Atlantic
PEPCO local plan submission for 2024 RTEP p. 9
Buzzard Point 13B & 14B Breaker Replacements “Replace the existing 138kV oil circuit breakers 13B & 14B at Buzzard Point.”
138kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this