Substation Scout

Hill Valley

Named in 1 PJM planning document for 1 project, on October 16, 2025.

Not stateddescribed as
PENELECzone
46 kVkV as printed
1mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Hill Valley - Huntingdon - Raystown 46 kV RAC Line
PN-2025-004
Not printed Not printed Not printed Not printed 2025-10-16
SRRTEP Mid-Atlantic

Every mention

DateDocumentProjectWhat the document says about it
2025-10-16 SRRTEP Mid-Atlantic
Item 05 - PENELEC Supplemental Projects p. 3
Hill Valley - Huntingdon - Raystown 46 kV RAC Line No role wording
46 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this