Glendale Industrial
In a case before the Kentucky Public Service Commission, “Glendale Megasite transmission facilities (Ford / SK Innovation battery plants)” (case 2022-00066). The station's utility: Kentucky Utilities.
Described as new. The quoted wording calls this substation new. “a new 138kV/24.7 kV substation to be called the Glendale Industrial Substation” — Kentucky Utilities application, Case 2022-00066, p.3 (case 2022-00066)
Note. The application places it near the planned Ford facility at the end of both 138kV lines from Glendale South. The order says it will transform 138 kV to Ford's required 24.7 kV at its load center and support future 138 kV network interconnections. Estimated cost approximately $25 million, excluding behind-the-meter assets Ford pays for.
Note. The Commission granted the CPCN on 2022-07-28.
County: “authorizing it to construct the following transmission facilities in Hardin County, Kentucky: 1. Two new 345-kilovolt (kV) transmission lines (an Eastern line and a Western line); 2. Two new 138 kV transmission lines; and 3. Two associated substations, “Glendale South Substation” and “Glendale Industrial Substation”.” — Commission final order, Case 2022-00066, p.1 (case 2022-00066).
Generation interconnection requests filed in Hardin, KY: PJM queue, 1 active of 14 · LG&E and KU queue, 2 active of 4. Same county, not the same substation.
Source: Kentucky Public Service Commission case records (psc.ky.gov): 36 transmission and substation cases filed since 2022 read by hand, 20 documents cited. Latest document dated November 13, 2026; retrieved 2026-11-21; records reviewed by hand 2026-11-21.
Before relying on any of this
- These are the substations named in Kentucky Public Service Commission cases since 2022: a utility files for a certificate when it builds most new transmission. Smaller substations, and projects that need no certificate, are not in these cases.
- A county is shown where the case prints it for the station; otherwise it is left blank.
- An application describes what a utility asks to build. Where the Commission has ruled, the page says so; an in-service date is the one the documents print, not a construction schedule.