Substation Scout

Navy

Named in 2 PJM planning documents for 1 project, from March 18, 2026 to September 17, 2026.

Not stateddescribed as
JCPLzone
34.5 kVkV as printed
2mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Lakehurst 34.5 kV Substation, NJ
JCPL-2026-006
Conceptual $4.23 M 03/15/2029 Not printed 2026-09-17
SRRTEP Mid-Atlantic

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named LAKEHURST; NAVY; SHIP TEST → LAKEHURST; NAVY; SHIP TEST; SOUTH LAKEWOOD 2026-03-18 2026-09-17

Every mention

DateDocumentProjectWhat the document says about it
2026-09-17 SRRTEP Mid-Atlantic
Item 01 - JCPL Supplemental Projects p. 25
Lakehurst 34.5 kV Substation, NJ No role wording
34.5 kV
2026-03-18 SRRTEP Mid-Atlantic
Item 06 - JCPL Supplemental Projects p. 3
Lakehurst 34.5 kV Substation, NJ No role wording
34.5 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.