Little Silver

Named in 1 PJM planning document for 1 project, on Not reported.

Not stateddescribed as
JCPLzone
34.5 kVkV as printed
1mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Automatic Restoration Projects
JCPL-2023-040 · s3250.1
Not printed $1.28 12/31/2027 Not printed 2026-09-08*
SRRTEP Mid-Atlantic

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named RED BANK → LITTLE SILVER; RED BANK 2024-10-08 Not reported

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Mid-Atlantic
JCPL local plan submission for 2024 RTEP p. 15
Automatic Restoration Projects No role wording
34.5 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.