Named in 1 PJM planning document for 1 project, on November 4, 2025.

Not stateddescribed as
JCPLzone
—kV as printed
1mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Kittatinny Substation
JCPL-2025-006
Not printed Not printed Not printed 35 MW 2025-11-04
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2025-11-04 TEAC
Item 05 - JCPL Supplemental Projects p. 4
Kittatinny Substation No role wording