Pitts

Named in 3 projects in the 2025 GA ITS Ten-Year Plan (2026-2035).

—county (not printed)
—kV in the quote
GPCproject sponsor
3projects in the plan

The plan prints no county for this substation, and no utility project page found names one for it.

Projects naming this substation

As the plan prints them. The sponsor is the project’s; one project can split work between owners.

ProjectSponsorWhere in the planNeed dateChange from the previous planSubstations named
BONAIRE PRIMARY - KATHLEEN 230kV LINE REBUILD
Rebuild the Bonaire Primary - Kathleen 230kV line (approximately 6 miles) with 200C 1351 ACSS conductor. Upgrade limiting elements at substation along the Kathleen - Pitts 230kV line.
TEAMS 20512 · plan p.89 · zone 214
GPC In the plan
p.7
Jun 1, 2026 No change Bonaire Primary, Kathleen, Pitts
FITZGERALD - PITTS 115kV LINE PARTIAL REBUILD
Rebuild the Pitts to Whittle segment, 9.1 miles of the Fitzgerald - Pitts 115kV line with 200C 1351 ACSS conductor and reconductor the Whittle to HWY 233 segment with 100 762 ACSR conductor.
TEAMS 21048 · plan p.161 · zone 214
GPC In the plan
p.13
Jun 1, 2028 No change Fitzgerald, Pitts
NORTH TIFTON - PITTS 230kV LINE REBUILD
Rebuild the overloaded section (approximately 11 miles) of the North Tifton - Pitts 230kV line with 200C 1351 ACSS martin conductor and replace the limiting switches at Pitts with higher rating switches.
TEAMS 21675 · plan p.281 · zone 214
GPC In the plan
p.21
Jun 1, 2031 New project North Tifton, Pitts

Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.