Named in 1 project in the 2025 GA ITS Ten-Year Plan (2026-2035).

—county (not printed)
—kV in the quote
GPCproject sponsor
1projects in the plan

The plan prints no county for this substation, and no utility project page found names one for it.

Projects naming this substation

As the plan prints them. The sponsor is the project’s; one project can split work between owners.

ProjectSponsorWhere in the planNeed dateChange from the previous planSubstations named
FITZGERALD - PITTS 115kV LINE PARTIAL REBUILD
Rebuild the Pitts to Whittle segment, 9.1 miles of the Fitzgerald - Pitts 115kV line with 200C 1351 ACSS conductor and reconductor the Whittle to HWY 233 segment with 100 762 ACSR conductor.
TEAMS 21048 · plan p.161 · zone 214
GPC In the plan
p.13
Jun 1, 2028 No change Fitzgerald, Pitts

Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.