Kathleen

Named in 2 projects in the 2025 GA ITS Ten-Year Plan (2026-2035).

—county (not printed)
—kV in the quote
GPCproject sponsor
2projects in the plan

The plan prints no county for this substation, and no utility project page found names one for it.

Projects naming this substation

As the plan prints them. The sponsor is the project’s; one project can split work between owners.

ProjectSponsorWhere in the planNeed dateChange from the previous planSubstations named
KATHLEEN - PERRY 115kV LINE REBUILD
Rebuild the Kathleen - Perry 115kV line with 200C 1351 ACSS martin conductor. Replace the jumpers and switches along the Kathleen - Perry 115kV line with higher rated ones.
TEAMS 12680 · plan p.257 · zone 214
GPC In the plan
p.19
Jun 1, 2030 New project Kathleen, Perry
BONAIRE PRIMARY - KATHLEEN 230kV LINE REBUILD
Rebuild the Bonaire Primary - Kathleen 230kV line (approximately 6 miles) with 200C 1351 ACSS conductor. Upgrade limiting elements at substation along the Kathleen - Pitts 230kV line.
TEAMS 20512 · plan p.89 · zone 214
GPC In the plan
p.7
Jun 1, 2026 No change Bonaire Primary, Kathleen, Pitts

Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.