Kathleen
Named in 2 projects in the 2025 GA ITS Ten-Year Plan (2026-2035).
—county (not printed)
—kV in the quote
GPCproject sponsor
2projects in the plan
The plan prints no county for this substation, and no utility project page found names one for it.
Projects naming this substation
As the plan prints them. The sponsor is the project’s; one project can split work between owners.
| Project | Sponsor | Where in the plan | Need date | Change from the previous plan | Substations named |
|---|---|---|---|---|---|
| KATHLEEN - PERRY 115kV LINE REBUILD Rebuild the Kathleen - Perry 115kV line with 200C 1351 ACSS martin conductor. Replace the jumpers and switches along the Kathleen - Perry 115kV line with higher rated ones. TEAMS 12680 · plan p.257 · zone 214 |
GPC | In the plan p.19 |
Jun 1, 2030 | New project | Kathleen, Perry |
| BONAIRE PRIMARY - KATHLEEN 230kV LINE REBUILD Rebuild the Bonaire Primary - Kathleen 230kV line (approximately 6 miles) with 200C 1351 ACSS conductor. Upgrade limiting elements at substation along the Kathleen - Pitts 230kV line. TEAMS 20512 · plan p.89 · zone 214 |
GPC | In the plan p.7 |
Jun 1, 2026 | No change | Bonaire Primary, Kathleen, Pitts |
Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.
Before relying on any of this
- The plan prints no county for a substation. A county shown here is printed in the plan beside the station, or on a Georgia Power or Georgia Transmission project page that names the same station and one county.
- Project Sponsor belongs to the project, not to each station; one project can split work between owners.
- Costs are redacted in the public version of the plan and are not shown.