Sonterra

Named in 2 listed projects in ERCOT’s transmission project tracking workbook, in Williamson County. First named in the release with data as of October 1, 2024.

Williamsoncounty as printed
138kV
ONCORutility
2projects listed

A HIFLD substation record has the same name and county: SONTERRA (WILLIAMSON County). The names agree; that does not confirm they are the same facility.

Generation interconnection requests filed in Williamson, TX: ERCOT queue, 1 active of 3. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Upgrade the Hutto & Round Rock - Salado 138 kV Line
Rebuild and double-circuit the Georgetown East - Sonterra 138 kV Line Section
ERCOT project 80546C · utility no. R6203, R6202 · RPG 24RPG018, 25RPG006 · RTP 2023-SC17
ONCOR
Tier 3
Planned
Future tab
138 May 2027 Georgetown East to Sonterra
Williamson County
Georgetown East, Sonterra
Upgrade the Hutto & Round Rock - Salado 138 kV Line
Rebuild and double-circuit the Sonterra - Salado 138 kV Line Section. Establish Salado 138 kV Switch and the Salado Switch - Round Rock Switch 138 kV Line
ERCOT project 80546D · utility no. R6203, R6202 · RPG 24RPG018, 25RPG006 · RTP 2023-SC17
ONCOR
Tier 3
Planned
Future tab
138 May 2027 Sonterra to Salado Switch
Williamson County
Sonterra, Salado Switch

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202680546CMoved between tabsCurrent-year planned → Future
October 1, 202680546CProjected in-service dateDec 2026 → May 2027
February 1, 202680546CMoved between tabsFuture → Current-year planned
February 1, 202680546CProjected in-service dateMay 2026 → Dec 2026
February 1, 202680546DProjected in-service dateDec 2026 → May 2027
June 1, 202580546DProjected in-service dateDec 2027 → Dec 2026
February 1, 202580546DProjected in-service dateDec 2026 → Dec 2027
October 1, 202480546CFirst listedon the Future tab
October 1, 202480546DFirst listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.