Named in 2 listed projects in ERCOT’s transmission project tracking workbook, in Williamson County. First named in the release with data as of October 1, 2015.

Williamsoncounty as printed
138kV
ONCORutility
2projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Williamson, TX: ERCOT queue, 1 active of 3. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Upgrade the Hutto & Round Rock - Salado 138 kV Line
Rebuild and double-circuit the Round Rock Westinghouse - Georgetown East 138 kV Line Section
ERCOT project 80546B · utility no. R6203, R6202 · RPG 24RPG018, 25RPG006 · RTP 2023-SC17
ONCOR
Tier 3
Planned
Current-year planned tab
138 May 2026 Round Rock Westinghouse Tap to Georgetown East
Williamson County
Round Rock Westinghouse Tap, Georgetown East
Upgrade the Hutto & Round Rock - Salado 138 kV Line
Rebuild and double-circuit the Georgetown East - Sonterra 138 kV Line Section
ERCOT project 80546C · utility no. R6203, R6202 · RPG 24RPG018, 25RPG006 · RTP 2023-SC17
ONCOR
Tier 3
Planned
Future tab
138 May 2027 Georgetown East to Sonterra
Williamson County
Georgetown East, Sonterra

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202680546CMoved between tabsCurrent-year planned → Future
October 1, 202680546CProjected in-service dateDec 2026 → May 2027
February 1, 202680546BProjected in-service dateDec 2025 → May 2026
February 1, 202680546CMoved between tabsFuture → Current-year planned
February 1, 202680546CProjected in-service dateMay 2026 → Dec 2026
June 1, 202580546BMoved between tabsFuture → Current-year planned
October 1, 202480546BProjected in-service dateMay 2026 → Dec 2025
October 1, 202480546CFirst listedon the Future tab
June 1, 202480546BFirst listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.