Cedar Creek
Named in 2 listed projects in ERCOT’s transmission project tracking workbook, in Wharton County. First named in the release with data as of June 1, 2021.
Whartoncounty as printed
345kV
CNPutility
2projects listed
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in Wharton, TX: ERCOT queue, 42 active of 44. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| This models the new CEHE Raider Substation and upgrades required for a proposed load addition Install new 345kV CEHE Raider substation. Loop 345 kV Ckt. 72 Bailey-Cedar Creek line into the new 345 kV Raider substation. Upgrade line relaying on Ckt 72 Cedar Creek-Raider-Bailey. Remove temporary 138 kV service. ERCOT project 110068A |
CNP Tier 4 |
Planned Future tab |
345 | May 2027 | Raider to Cedar Creek/Bailey Wharton County |
Raider, Cedar Creek, Bailey |
| Buffalo Creek BESS (26INR0405) at Cedar Creek 345kV CEHE Substation Interconnect new generation facility for Buffalo Creek BESS (26INR0405) at Cedar Creek 345kV CEHE Substation. Utilize existing generator lead. Remove existing generator lead conductor and install new bundled 959ACSS conductor. ERCOT project 99397 |
CNP Tier 4 |
In-Service Completed tab |
345 | Dec 2025 actual 2025-12 |
Cedar Creek to Buffalo Creek Wharton County |
Cedar Creek, Buffalo Creek |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| October 1, 2026 | 110068A | Moved between tabs | Current-year planned → Future |
| October 1, 2026 | 110068A | Status as reported | Conceptual → Planned |
| October 1, 2026 | 110068A | Projected in-service date | Oct 2026 → May 2027 |
| July 13, 2026 | 110068A | First listed | on the Current-year planned tab |
| February 1, 2026 | 99397 | Moved between tabs | Current-year planned → Completed |
| February 1, 2026 | 99397 | Status as reported | Planned → In-Service |
| February 1, 2026 | 99397 | Projected in-service date | Nov 2025 → Dec 2025 |
| October 1, 2025 | 99397 | First listed | on the Current-year planned tab |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.