Substation Scout

Buffalo Creek

Named in 1 listed project in ERCOT’s transmission project tracking workbook. First named in the release with data as of October 1, 2025.

—county as printed
345kV
CNPutility
1projects listed

No HIFLD substation record has this name in this county.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Buffalo Creek BESS (26INR0405) at Cedar Creek 345kV CEHE Substation
Interconnect new generation facility for Buffalo Creek BESS (26INR0405) at Cedar Creek 345kV CEHE Substation. Utilize existing generator lead. Remove existing generator lead conductor and install new bundled 959ACSS conductor.
ERCOT project 99397
CNP
Tier 4
In-Service
Completed tab
345 Dec 2025
actual 2025-12
Cedar Creek to Buffalo Creek
Wharton County
Cedar Creek, Buffalo Creek

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
February 1, 202699397Moved between tabsCurrent-year planned → Completed
February 1, 202699397Status as reportedPlanned → In-Service
February 1, 202699397Projected in-service dateNov 2025 → Dec 2025
October 1, 202599397First listedon the Current-year planned tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.

Before relying on any of this

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first