Riverton

Named in 2 listed projects in ERCOT’s transmission project tracking workbook, in Reeves County. First named in the release with data as of February 1, 2016.

Reevescounty as printed
138, 345kV
ONCORutility
2projects listed

Also printed as: Riverton Switch

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Reeves, TX: ERCOT queue, 24 active of 27. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Riverton-Border-Quarry Field 138 kV Second Circuit
Add Permian Basin Reliability Plan Upgrade ID L1A and L1D Riverton-Border-Quarry Field 138 kV Second Circuit
ERCOT project 81060 · utility no. R8733
ONCOR
Tier 4
In-Service
Completed tab
138 Dec 2025
actual 2025-12
Riverton to Quarry Field
Reeves / Loving County
Riverton, Quarry Field
Construct Drill Hole – Riverton 345 kV Double-Circuit
ERCOT project 87021 · utility no. R8748 · RPG 24RPG010
ONCOR
Tier 1
Planned
Future tab
345 Dec 2027 Drill Hole Switch to Riverton Switch
Culberson / Reeves County
Drill Hole Switch, Riverton Switch

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
February 1, 202681060Moved between tabsCurrent-year planned → Completed
February 1, 202681060Status as reportedPlanned → In-Service
June 1, 202581060Moved between tabsFuture → Current-year planned
February 1, 202587021Projected in-service dateDec 2026 → Dec 2027
October 1, 202487021First listedon the Future tab
June 1, 202481060First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.