Faulkner

Named in 4 listed projects in ERCOT’s transmission project tracking workbook, in Reeves County, plus 1 on its Cancelled tab. First named in the release with data as of February 1, 2022.

Reevescounty as printed
138, 345kV
AEP TNC/TNMP, TNMPutility
4projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Reeves, TX: ERCOT queue, 24 active of 27. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Double Ckt Line M138-K
Project Delayed Indefinitely.
ERCOT project 65663
TNMP
Tier 4
Planned
Future tab
138 Dec 2032 Pecos (bus # 38091) to Faulkner (bus # 38124)
Reeves County
Pecos, Faulkner
Cryo to Faulkner: Construct New 138 kV Line
Construct a new 138 kV single circuit line from Cryo to Faulkner
ERCOT project 91937 · utility no. TP2025146 · RPG H.B. 5066
AEP TNC/TNMP
Tier 2
Planned
Future tab
138 Aug 2029 Cryo to Faulkner
Reeves County
Cryo, Faulkner
Solstice to Faulkner: Construct New 345 kV Double Circuit Line
Construct a new 345 kV double circuit line from Solstice to Faulkner
ERCOT project 91941 · utility no. TP2024165 · RPG H.B. 5066
AEP TNC/TNMP
Tier 1
Planned
Future tab
345 Oct 2029 Solstice to Faulkner
Pecos / Reeves County
Solstice, Faulkner
Faulkner - Cryo 138kV - Part of Upgrade L4 2024 Permian Basin Study
ERCOT project 92282
TNMP
Tier 2
Planned
Future tab
138 Jun 2030 No terminals printed
Reeves County
Faulkner, Cryo

On the Cancelled tab

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Interconnects Faulkner Data Center
Project has been cancelled.
ERCOT project 65648
TNMP
Tier 4
Planned
Cancelled tab
138 Oct 2029 TNMP Faulkner (bus # 38124) to Customer substation (bus # 38125)
Reeves County
Faulkner

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202691937Projected in-service dateJan 2029 → Aug 2029
July 13, 202665663Moved between tabsCurrent-year planned → Future
July 13, 202665663Projected in-service dateJun 2026 → Dec 2032
February 1, 202665663Moved between tabsFuture → Current-year planned
February 1, 202691941Projected in-service dateDec 2030 → Oct 2029
October 1, 202591937Projected in-service dateDec 2030 → Jan 2029
June 1, 202591937First listedon the Future tab
June 1, 202591941First listedon the Future tab
June 1, 202592282First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.