Faulkner
Named in 4 listed projects in ERCOT’s transmission project tracking workbook, in Reeves County, plus 1 on its Cancelled tab. First named in the release with data as of February 1, 2022.
Reevescounty as printed
138, 345kV
AEP TNC/TNMP, TNMPutility
4projects listed
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in Reeves, TX: ERCOT queue, 24 active of 27. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Double Ckt Line M138-K Project Delayed Indefinitely. ERCOT project 65663 |
TNMP Tier 4 |
Planned Future tab |
138 | Dec 2032 | Pecos (bus # 38091) to Faulkner (bus # 38124) Reeves County |
Pecos, Faulkner |
| Cryo to Faulkner: Construct New 138 kV Line Construct a new 138 kV single circuit line from Cryo to Faulkner ERCOT project 91937 · utility no. TP2025146 · RPG H.B. 5066 |
AEP TNC/TNMP Tier 2 |
Planned Future tab |
138 | Aug 2029 | Cryo to Faulkner Reeves County |
Cryo, Faulkner |
| Solstice to Faulkner: Construct New 345 kV Double Circuit Line Construct a new 345 kV double circuit line from Solstice to Faulkner ERCOT project 91941 · utility no. TP2024165 · RPG H.B. 5066 |
AEP TNC/TNMP Tier 1 |
Planned Future tab |
345 | Oct 2029 | Solstice to Faulkner Pecos / Reeves County |
Solstice, Faulkner |
| Faulkner - Cryo 138kV - Part of Upgrade L4 2024 Permian Basin Study ERCOT project 92282 |
TNMP Tier 2 |
Planned Future tab |
138 | Jun 2030 | No terminals printed Reeves County |
Faulkner, Cryo |
On the Cancelled tab
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Interconnects Faulkner Data Center Project has been cancelled. ERCOT project 65648 |
TNMP Tier 4 |
Planned Cancelled tab |
138 | Oct 2029 | TNMP Faulkner (bus # 38124) to Customer substation (bus # 38125) Reeves County |
Faulkner |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| October 1, 2026 | 91937 | Projected in-service date | Jan 2029 → Aug 2029 |
| July 13, 2026 | 65663 | Moved between tabs | Current-year planned → Future |
| July 13, 2026 | 65663 | Projected in-service date | Jun 2026 → Dec 2032 |
| February 1, 2026 | 65663 | Moved between tabs | Future → Current-year planned |
| February 1, 2026 | 91941 | Projected in-service date | Dec 2030 → Oct 2029 |
| October 1, 2025 | 91937 | Projected in-service date | Dec 2030 → Jan 2029 |
| June 1, 2025 | 91937 | First listed | on the Future tab |
| June 1, 2025 | 91941 | First listed | on the Future tab |
| June 1, 2025 | 92282 | First listed | on the Future tab |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.